Case studies
- The U.S.
- Japan
- S.E.A.
Southeast
9Southwest
5
Sample U.S. projects under development by Solariant Capital
![](/static/images/case-studies/usa/south-east/project-south-east-new-river-solar.webp?version=7d60e6046884e0916bb68b1983cc4a7d5f2aa459)
New River Solar
Bradford County, Florida
74.9 MW Solar + 70 MW
- Development Status: Site Control executed, Interconnection System Impact Study in progress, Critical Issues Analysis Complete.
- Expected Commercial Operation Date NTP: September 2025, COD: September 2026
![](/static/images/case-studies/usa/south-east/project-south-east-pleasant-solar.webp?version=7d60e6046884e0916bb68b1983cc4a7d5f2aa459)
Pleasant Solar
Alachua County, Florida
74.9MW Solar + 70 MW
- Development Status: Site Control Secured, LGIA Executed & Suspended, Starting City Site Plan & Special Exception Permitting.
- Expected Commercial Operation Date NTP: July 2025, COD: June 2026
![](/static/images/case-studies/usa/south-east/project-south-east-racetrack-solar.webp?version=7d60e6046884e0916bb68b1983cc4a7d5f2aa459)
Racetrack Solar
Alachua County, Florida
74.9 MW Solar + 70 MW
- Development Status: Site Control executed, GRU accepted IR, Initial Permitting & Environmental site work started.
- 2025 NTP: June 2026, COD: June 2027
![](/static/images/case-studies/usa/south-east/project-south-east-wakulla-solar.webp?version=7d60e6046884e0916bb68b1983cc4a7d5f2aa459)
Wakulla Solar
Wakulla County, Florida
74.9 MW Solar + 70 MW
- Development Status: Site Control executed, Interconnection Request Submitted & studies in process, Critical Issues Analysis & Phase 1 ESA Complete.
- Expected Commercial Operation Date NTP: December 2025, COD: December 2026
![](/static/images/case-studies/usa/south-east/project-south-east-canoochee-river-solar.webp?version=7d60e6046884e0916bb68b1983cc4a7d5f2aa459)
Canoochee River Solar
Emanuel County, Georgia
150 MW Solar + 45 MW
- Development Status: Site Control executed, Interconnection Request submitted, Critical Issues Analysis & Phase 1 ESA in progress.
- Expected Commercial Operation Date NTP: November 2027,COD: November 2028
![](/static/images/case-studies/usa/south-east/project-south-east-red-dirt-solar.webp?version=7d60e6046884e0916bb68b1983cc4a7d5f2aa459)
Red Dirt Solar
Talbot County, Georgia
150MW Solar + 75MW/300MWh Storage
- Development Status: Site Control Option Executed, System Impact Study in process, Critical Issues Analysis completed, Phase I ESA completed.
- Expected Commercial Operation Date NTP: November 2027, COD: November 2028
![](/static/images/case-studies/usa/south-east/project-south-east-southern-sky-solar.webp?version=7d60e6046884e0916bb68b1983cc4a7d5f2aa459)
Southern Sky Solar
Clinch County, Georgia
100 MW Solar + 50 MW
- Development Status: Site Control executed, System Impact Study in Process, Critical Issues Analysis complete & Phase I ESA completed.
- Expected Commercial Operation Date NTD: September 2027, COD: September 2028
![](/static/images/case-studies/usa/south-east/project-south-east-two-river-solar.webp?version=7d60e6046884e0916bb68b1983cc4a7d5f2aa459)
Two Rivers Solar
Camden County, Georgia
100 MW Solar + 50 MW
- Development Status: Site Control executed, Interconnection System Impact Study Completed, Facilities Study in progress, Critical Issues Analysis and Phase 1 ESA complete.
- Expected Commercial Operation Date NTP: April 2026, COD: September 2027
![](/static/images/case-studies/usa/south-east/project-south-east-rochester-road-solar.webp?version=7d60e6046884e0916bb68b1983cc4a7d5f2aa459)
Rochester Road Solar
Butler County, Kentucky
115 MW Solar + 50 MW / 200 MWh Storage
- Development Status: Site Control executed, System Impact Study in Progress, Critical Issues Analysis Completed.
- Expected Commercial Operation Date NTP: November 2025, COD: November 2026